AGP Picks
View all

USACE-Albuquerque District, White Sands Missile Range break ground on microgrid power project

News originally published by

DVIDS - Georgia

WHITE SANDS MISSILE RANGE, N.M. – Representatives from the U.S. Army Corps of Engineers-Albuquerque District joined White Sands Missile Range leadership and contractor representatives to break ground on the Stallion Range Power Generation and Microgrid project, Nov. 10, 2026.

The project will be located on the missile range’s Stallion Base Camp on the northern part of the range.

“Today we mark the groundbreaking of the Stallion Range Power Generation and Microgrid project,” said Lt. Col. Brian Williams, commander, USACE-Albuquerque District. “This $27 million military construction project is part of the Energy Resilience and Conservation Investment Program and was awarded this August in direct execution of the Army Directive on U.S. Army Installation Energy and Water Resilience Policy.”

The microgrid includes a 600-kW solar photovoltaic array, as well as propane generators and a 500-kW battery energy storage system. When completed, it will provide four facilities at the Stallion Base Camp with 14 days of energy and potable water during extended power outages.

“This investment ensures that critical test data is collected, test schedules remain intact, and operational readiness is maintained,” said Col. Michael Lueckeman, White Sands Missile Range garrison commander.

The USACE project delivery team utilized a “team of teams” approach with the Louisville District serving as the contracting authority, the USACE Huntsville Center providing technical design support, and the Albuquerque District leading construction oversight and field administration.

According to Williams, the Albuquerque District, WMSR garrison team, and construction contractor partners are working to ensure seamless execution and deliver the project within 17 months.

The Albuquerque District has previously partnered with WSMR on similar projects, completing a $10.6 million Design Bid Build project for the installation of a microgrid system for four potable water wells on the range in 2025.

A microgrid is a self-sufficient energy system that serves a specific geographic area. It can be attached to a centralized national grid, but it’s able to function independently.

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

Power Generation Journal

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.